Thursday, June 24, 2010

Day 163 & 164: Duct heating vents installed and lock up inspection

Hi friends,

I had a pre-plaster inspection with my independent building inspector on the 23.06.2010 and there were a number of defects found some are cosmetic and some are structural, most of them are easily fixed. The serious ones are: some of the wall bracings had been cut therefore new ones need to be installed, in some places the truss is not sitting on studs therefore extra studs are added to the existing studs that are close by for support, missing noggings etc. Most of the other defects are acid stains to brick mortar, crack brick mortar in some places, acid stain to bricks, gaps between gutter barge and wall, eave corner was installed short. Also the heating guys were there installing the duct heating vents.

Today 24.06.2010 the carpenters came to fix the internal defects found at the lock-up inspection , the external defects hasn't been fixed yet but hopefully soon. A big thank you to my new site supervisor acknowledging and accepting to fix the defects without any hassles or complaints and for getting the carpenters in quickly to fix the defects.

Other works done were the electrician came back to re-install the alfresco powerpoint as it was to high, install electrical junction box above the kitchen side sliding door for future external light fitting.

No comments:

Post a Comment