Tuesday, June 8, 2010

Day 148: Fibre cement, timbers, and doors delivered

Hi friends,

We are a step closer to completion of lockup stage with the internal garage and rear garage doors delivered however they still haven't finish bricking the wall above the rear garage door, the porch, and the feature masonary block at the front of the house. There's not much bricking to do so I don't understand why they just don't finish it. In addition, the bricks hasn't been cleaned yet, and they haven't put in the foam sheet into the articulated joint for bedroom 2 and bedroom 3 wall, they will need to ask my neighbour to allow them access to get the work done. Anyway they also delivered the fibre cement sheeting for the eaves, and I think they delivered the villaboards for the internal garage walls. I hope they won't install the villaboards yet as they still haven't fix the frame overhang.
They also delivered more timber for framing, my guess this is for the lock up carpenter to use when he goes around fixing the frames.