Day 45: We have partial frame

Hi friends,

More work was done today with the chippies putting up the frames around the slab. There are certain spots that need to be completed but majority are done. I measured the dimension of each room and it's pretty much spot on except for the living room where it is short about 240mm (24cm), it looks like someone haven't check the measurement correctly before pouring the slab. So lesson number 1. You should go and measure the dimension of the formwork to see if it is the same as the slab plan before the concrete is poured. Oh boy it's going to be fun dealing with HQ on how to fix this error.

Viewing front of house.

Walk in Robe and Ensuite

Ensuite.
View of family room from alfresco

View meal room from alfresco

KitchenLiving roomBathroom

Viewing from hallway into bedroom 2 and entry to bedroom 3

Bedroom 3
Toilet, laundry, and bedroom 4

Bedroom 4
Oops a bit short